County Road Closings

UPDATE: A portion of County Road 1600 in Montgomery Township remains closed for a bridge replacementThe road is closed between County Road 1775 and Township Road 655.   Estimated reopening date is now June 22. 

NEW: A portion of Township Road 555 in Vermillion Township will be closed Monday, June 8th through Tuesday, June 9th for a culvert replacement.  The road will be closed overnight between County Road 2000 and County Road 30A.  More specifically between house # 2000 and house # 1984.  It is anticipated that the road will reopen by the end of the day on Tuesday, June 9th.

 

                                        For State Road Closings see                                         Ohio Department of Transportation Traffic Roadway Information

 


County Road Work

Pavement Marking - 2026
Description: Annual – Placement of pavement markings on all Ashland County-maintained roads.
Funding:  100% Local funds
Estimated construction timeframe: Summer – Fall 2026
Work to be performed by JD Striping & Services chosen by competitive bid process.
 
Sealing - 2026
Description: Annual Project Applying Liquid Asphalt and Stone
Funding: 100% Local funds
Estimated construction timeframe: Summer 2026
Work to be performed by Sarver Paving Co. chosen by competitive bid process.
Traffic will be maintained at construction sites. 
Locations:  TBA
--------------------
Summer 2027 - Bridges
Bridge 1550-50
Description: Replacement. Complete road closure, detours will be marked.
Location: Township Road 1550 east of Township Road 65 in Perry Township
Estimated construction timeframe: 120 day closure
Funding:  95% State Funds, 5% Local Funds
Work to be performed by a Contractor determined by competitive bid process.
--------------------
Pavement Marking - 2028
Description: Annual – Placement of pavement markings on all Ashland County-maintained roads.
Funding:  100% CSTP for first $448,000, 100% Local funds any over $448,000
Estimated construction timeframe: Summer – Fall 2028
Work to be performed by a Contractor determined by competitive bid process.
--------------------
Roundabout CR 1356 and CR 1153 - 2028
Description: Installation of roundabout at intersection with high crash incidents
Funding:  90% Federal, 10% Local funds - engineer's estimate $3,052,000.00
Estimated construction timeframe: Summer – Fall 2028 or 2029
Work to be performed by a Contractor determined by competitive bid process.
--------------------
Guardrail - 2029
Description: Install new and upgrade existing guardrail to meet current standards on select sections of Ashland County-maintained roads.
Funding: 100% HSIP funds first $300,000; 100% Local funds any over $300,000
Estimated construction timeframe: Summer 2029
Work to be performed by a Contractor determined by competitive bid process.
Traffic will be maintained at construction sites. 
Most sites will be affected for less than 1 day.
Locations: TBA
--------------------
Guardrail - 2030
Description: Install new and upgrade existing guardrail to meet current standards on select sections of Ashland County-maintained roads.
Funding: 100% HSIP funds first $300,000; 100% Local funds any over $300,000
Estimated construction timeframe: Summer 2030
Work to be performed by a Contractor determined by competitive bid process.
Traffic will be maintained at construction sites. 
Most sites will be affected for less than 1 day.
Locations: TBA
--------------------
Pavement Marking - 2030
Description: Annual – Placement of pavement markings on all Ashland County-maintained roads.
Funding:  100% CSTP for first $352,000, 100% Local funds any over $352,000
Estimated construction timeframe: Summer – Fall 2030
Work to be performed by a Contractor determined by competitive bid process.
--------------------
Guardrail - 2031
Description: Install new and upgrade existing guardrail to meet current standards on select sections of Ashland County-maintained roads.
Funding: 100% HSIP funds first $300,000; 100% Local funds any over $300,000
Estimated construction timeframe: Summer 2031
Work to be performed by a Contractor determined by competitive bid process.
Traffic will be maintained at construction sites. 
Most sites will be affected for less than 1 day.
Locations: TBA
 

Published on  June 3rd, 2026